The Certified Payroll report provides a review of certified payroll records for contractors and subcontractors required by Federal or Federally-aided construction-type contracts and subcontracts to submit weekly payrolls. This report generates records only for customers listed as Certified Payroll and displays detailed regular and overtime hours for each day of the working week, along with gross and net earnings and itemized deductions.
Report Description
The Certified Payroll report is used to review certified payroll records. Certified Payroll records are made available for contractors and subcontractors required by their Federal or Federally-aided construction-type contracts and subcontracts to submit weekly payrolls. This report generates records only for customers listed in Certified Payroll.
Certified Payroll shows detailed regular and overtime hours for each day of the working week. It also shows the gross and net amount earned by an employee and provides itemized deductions included in net pay.
Parameters
| Parameter Name | Options | Explanation |
|---|---|---|
| Branch | All available branches | |
| SSN | Filters results by employee | |
| Date Type | Accounting Period Date, Week End Date | Transaction Accounting Period Date or Week Worked |
| Date | Select Accounting Period Date or Week End Date | |
| Project Name | Filters results by Project Name [Customer Extra >> Project Name copied onto Transaction Extra] | |
| Payroll Number | Enter the payroll number to appear on the report. | |
| Fringe Benefits - Paying Cash in Lieu? | Yes, No, Not Applicable |
|
Report Fields
| Field Name | Explanation |
|---|---|
| Page 1 | |
| Contractor check box | By default unchecked |
| Subcontractor check box | By default checked |
| Name of Subcontractor | Staffing company of check received by employee |
| For Week Ending | Transaction Week Worked Date |
| Address | Full address of staffing company of check |
| OMB No. | By default '1235-0008' |
| Expires | By default '02/28/2018' |
| Project and Location | Displays Project Name and Customer Worksite Address |
| Order ID | Order ID of staffing order linked to transaction |
| Project or Contract No. |
First pulls from PO Management / Transaction Snapshot. If null, pulls from PO Number Extra (Category = CustomerOrderExtra, SystemName = InvoiceExtra1). Check whether Copy to Transaction is enabled. If still null, pulls from Project Number Extra, then from Transaction Extra > Project Number. |
| Name of Individual | Employee name |
| No. of Withholding Exemptions | Exemptions for Federal Tax from Employee Tax setup |
| Work Classification | Job title from order |
| Day and Date |
Seven columns, one per day, showing regular and OT hours worked in the week. Column headers update dynamically based on the date selected in the parameter. The date and first letter of the weekday name display in the header. Example: If Week Worked = 9/3/2016, headers display as: S28 | M29 | T30 | W31 | T1 | F2 | S3 |
| O | Daily OT hours |
| S | Daily regular (straight) hours |
| Total Hours | Total OT hours in O row; total regular hours in S row |
| Rate of Pay |
When Fringe Benefits - Paying Cash in Lieu is set to No: Row S: Reg Pay Rate + Fringe Pay Rate (shown separately) Row O: OT Pay Rate + Fringe OT Pay Rate (combined) |
| Gross Amount Earned |
Top row: Gross wage from transaction Bottom row: Gross amount from check |
| Deductions |
Six deduction columns:
|
| Total Deductions | FICA + Withholding Tax + Med + State + Other |
| Net Wages Paid for Week | Net amount from check |
| Page 2 | |
| Date | Report run date |
| Name of Signature Party | Supplier property: CertifiedPayroll_UserName |
| Title | Supplier property: CertifiedPayroll_Title |
| Employed by... | Staffing company name |
| On the... | Customer name |
| Commencing on the... | First and last day of the week |
| On behalf of said... | Staffing company name |
| Name and Title |
Name: username of user who ran the report Title: by default PayrollAdmin |
Required Setup
Complete the following setup steps before running the Certified Payroll report. Setup is required for the report to generate correctly.
1. Transaction Type Setup
Add fringe rate transaction types in Admin Tools:
- Fringe Reg — set System Name to
Fringe - Hourly Rate - Fringe OT — set System Name to
Fringe - OT
2. Config Choice Setup
Add Config Choice options in Admin Tools using the Config Choice Options guide.
Create the following Config Choice entries:
-
Project Number — set up under Customer Extra
- Category:
CustomerOrderExtra - SystemName:
ProjectNumber
- Category:
-
InvoiceExtra1 — used to pull PO Number from Transaction Extra
- Category:
CustomerOrderExtra - SystemName:
InvoiceExtra1
- Category:
-
Project Name — set up under Customer Extra
- Category:
CustomerOrderExtra - SystemName:
ProjectName
- Category:
Once a Config Choice has been created, add the SystemName under the ChoiceProperty tab:
- Go to Admin Tools > System > Config Choice > ChoiceProperty.
- Set Category to
CustomerOrderExtra. - Under Select Branch, select any branch that needs access to this Config Choice.
- Set ChoiceCode to
ProjectName. - Under SystemName, enter:
Project Name. - Check Apply changes to all Branches if needed.
- Select Save.
3. Customer Setup
Enable Certified Payroll at the customer level.
- Go to Main Menu > Customer (confirm you are on the correct customer office).
- Select Sales & Service > Service Info.
- Check the Certified Payroll box.
- Tab off to save.
4. Job Order Setup
Certified Payroll must also be enabled at the job order level.
- Go to Main Menu > Order > Search Order ID > Detail > More Info (right side menu tab).
- Check the Certified Payroll box.
- Tab off to save.
5. Project Name Setup (Job Order Level)
The Project Name must be added at the job order level for it to pull into the report correctly.
- Go to Main Menu > Order > Extra.
- Set Label to
Certified Project Name. - Under Value, enter the project name.
- Tab off to save.
Running the Certified Payroll Report
This completes the setup for Certified Payroll. Keep the following in mind when processing and running the report:
- Certified Payroll transactions must be processed in a separate Time Entry and Payroll batch. If processed alongside non-Certified Payroll transactions, they will not pull into the report.
- You do not need to post the Payroll Batch for data to appear — only process it.
- When running the report, leave the Project Name field blank. Project Name data pulls from Job Order > Extra, along with any other job order extras added for Certified Payroll.
For additional reference, see: https://www.dol.gov/whd/forms/wh347instr.htm
3rd party link disclaimer: These links are provided as a convenience and for informational purposes only; they do not constitute an endorsement or approval by Avionté of any products, services, or opinions of the corporation or organization or individual. Avionté bears no responsibility for the accuracy, legality, or content of the external site or for subsequent links. Contact the external site for answers to questions regarding its content.
Comments
0 commentsPlease sign in to leave a comment.